Home/Services/Cylinders/No. 01Eight tie-rod cylinders, 96 hoses, and a workover rig that needed to be back on a well in 19 days.
Cylinders · Hoses · Oilfield🇦🇪 UAE · Jebel AliCASE NO. 01 · MAR 2026 · BAY 2 / ON-SITE

Eight tie-rod cylinders, 96 hoses, and a workover rig that needed to be back on a well in 19 days.

An ADNOC sub-contractor running a hydraulic workover unit in the Rub’ al Khali had four cylinders weeping at the gland, two hoses ruptured at the swage, and a recerts file three months overdue. We took the call on a Sunday. The unit was back skidding on a wellhead the third Friday after.

FIG. 01 · HWO-50K skid in JAFZA yard, day 2 — cylinders being broken outPHOTO · K. AL MARZOUQI · 2026-03-04
Asset
HWO-50K· 50 klb HWU
Cylinders
8· 6″ bore tie-rod
Hoses replaced
96· 4SP + 2SN
Turnaround
19days
H₂S service
NACE MR0175
/01

The problem on the rig.

The call came in at 22:14 on a Sunday. A 50,000-lb hydraulic workover unit had been pulled off a sour-gas well in the Rub’ al Khali because two main jack cylinders were weeping at the gland and a 1″ pressure hose had ruptured at the swage. The client had a slot booked at Habshan in three weeks. The clock was already running.

By Monday morning a transporter was rolling the unit into our Jebel Ali yard. The story we got was: “seal kits, please.” The story the unit told, once it was in the bay, was longer than that. Three of the four jack cylinders were out of straightness. Six hoses had cover degradation consistent with ambient temps north of 55 °C and a year on a rig without UV shrouds. The accumulator pre-charge file hadn’t been updated since the 2024 rainy season — there isn’t one in Abu Dhabi, but you know what we mean.

⚠ What the operator told us

“Weeping seals, one burst hose — seal kits, please.”

Two jack cylinders weeping at the gland, one pressure hose ruptured at the swage. Operator wanted a 5-day seal-and-swap and back on hire. They asked for parts. They did not ask for an engineer.

✓ What the inspection actually found

Three bent rods, 96 hoses end-of-life, recerts overdue

Rod straightness out on 3/4 jacks. Hose covers cracked across the boom run. Accumulator nitrogen + relief valves out of recert by 7 months — we couldn’t legally re-skid the unit on sour service without sign-off.

This is the case for sending an inspection engineer before you send a seal kit. The cheapest version of this job — the one the operator asked for — would have put the unit back on a wellhead with two cylinders that were going to fail inside a month, on a sour-gas job where failure is not a paperwork problem. We didn’t do that. We wrote it up properly, costed three options, and let the customer pick.

/02

What we did instead.

We rebuilt all eight tie-rod cylinders (four jacks, two snubbing, two travelling), replaced 96 hoses across the boom, jack circuit and accumulator manifold, repressurised the four accumulators with traceable nitrogen, and ran a closed-loop function test against the rig’s original commissioning sequence. Nineteen days, end to end, with three of our engineers on-site at JAFZA and two more on the bench in our Jebel Ali shop for the hose end-fitting work. Every assembly went out tagged, every test report sat on the customer’s rig manager’s desk before the unit was loaded.

Every hose was built in-house to EN 856 4SP on the high-pressure circuits, EN 853 2SN on the return and case-drain lines, and API 7K Grade D on the two rotary-line replacements. End fittings are 316 SS with NACE MR0175-compliant elastomers throughout — non-negotiable on sour service, and not a corner you cut to save a day.

FIG. 02Day 6 — JAFZA hose bay. Every assembly is laid out, tagged with circuit ID, swage number and proof-test record before it leaves the bench.
You can’t argue with sour service. NACE elastomers, 316 fittings, proof test on every assembly. The minute you cut a corner, you’re betting somebody’s life against three days of schedule.— Khalid Al Marzouqi · Field Lead · Jebel Ali
/03

How we approached it — the four phases.

Every workover-rig hydraulic overhaul we run in the Gulf goes through the same four phases. Names don’t change; the durations vary with how much we find on the bench.

PHASE 01

Mobilise & inspect

Engineer on rig within 24 h. Photo log, fluid sample, dimensional survey, recerts audit. Report on operator’s desk inside 48 h.

Days 0 — 2
PHASE 02

Quote & PO release

Three-option quote: minimum-fix, recommended, full-recert. Hose schedule attached, with EN/API/SAE specs called out per circuit.

Days 3 — 4
PHASE 03

Rebuild & assemble

Cylinders honed, rods chromed, sealed to NACE. 96 hoses built in JAFZA bay. Accumulators re-bladdered, N₂ recharged.

Days 5 — 14
PHASE 04

Function-test & release

Closed-loop test vs OEM commissioning sequence. Witnessed by client rep. Sign-off pack: 42 pages, two paper copies on the skid.

Days 15 — 19
/04

The SOP we followed, line by line.

Below is the actual SOP for a tie-rod cylinder & rig-hose overhaul on a sour-service workover unit — abridged. The full SOP-OG-014 runs 46 lines; this is the subset that was ticked off on this job, signed by the QA lead and counter-signed by the customer’s HSE rep.

SOP-OG-014 · HWU CYLINDER & HOSE OVERHAUL · REV 06 · NACE20 / 20 COMPLETE
Phase 01 · Mobilise & inspect
On-site inspection within 24 hEngineer dispatched from JAFZA yard; photo log, walk-around, fluid sample
K. AL MARZOUQI
Site visit
Sour-service classificationConfirmed H₂S partial pressure > 0.3 kPa — NACE MR0175 applies
QA
Gas data
Cylinder rod straightness survey3 of 4 jacks > 0.3 mm/m TIR — flagged for removal
QA
Dial gauge
Hose schedule audit96 assemblies inventoried by circuit, length, fitting, rated pressure
H. AL AWADI
Tag sheet
Recerts & pressure-vessel auditAccumulator N₂ pre-charge file 7 mo overdue; relief valves 4 mo overdue
QA
Recerts log
Phase 02 · Quote & PO release
Three-option intake report (PDF)22 pp · costed minimum, recommended, full-recert paths
Y. AL HASHIMI
PDF
Customer PO & LOI receivedRecommended-path PO; LOI on file dated 2026-03-06 09:40 GST
SALES
Email
Phase 03 · Cylinder rebuild
Disassemble 8× tie-rod cylinders4× jack 6″ bore, 2× snubbing 4½″ bore, 2× travelling 5″ bore — tagged by position
O. AL MAKTOUM
Workshop
Straighten & re-chrome 3× rodsPress-straightened to < 0.1 mm/m TIR; 80 µm hard chrome, ground to size
A. AL SUWAIDI
Press + lathe
Hone 8× barrels0.05 mm oversize bore; cross-hatch pattern at 45°, Ra 0.4 µm
A. AL SUWAIDI
Hone bar
Fit NACE-spec seal kitsHNBR rod & piston seals, FKM back-ups; all to MR0175
O. AL MAKTOUM
Press fit
Wet-test each cylinder at 1.5× MAWP525 bar held 30 min; leak-rate < 5 ml/min on all 8
QA
Closed-loop rig
Phase 04 · Hose build & install
Build 60× hi-pressure hoses · EN 856 4SP3/4″ & 1″ ID, 316 stainless fittings, proof-tested at 2× WP
H. AL AWADI
Crimp bay
Build 28× return-line hoses · EN 853 2SN1″ & 1¼″ ID, abrasion sleeve on boom run
H. AL AWADI
Crimp bay
Build 8× rotary lines · API 7K Grade D2″ ID, 5,000 psi WP, fire-resistant cover
H. AL AWADI
API bay
Tag & certify every assemblyEach hose: circuit ID, swage no., proof-test date, batch trace
QA
Tag printer
Re-pressurise 4× accumulators1,000 psi N₂ pre-charge, traceable bottle nos. on file
K. AL MARZOUQI
N₂ rig
Phase 05 · Function-test & release
Closed-loop function testFull skidding, jacking, snubbing sequence vs OEM commissioning script
QA
Test rig
Client-witnessed sign-offOperator HSE rep present; ADNOC vendor cert verified
Y. AL HASHIMI
On-site
Issue return packet42 pp · test curves, NACE certs, hose register, recerts, photos × 38
Y. AL HASHIMI
PDF + paper
/05

The numbers, before and after.

Below is what we actually measured on the cylinders and hose population, against OEM and API/EN tolerance. Four cylinder findings and two hose findings would have failed an audit — all six were fixed in Phase 03. Numbers in the as-found column are the worst-case reading per population; after-rebuild is the average across the eight units or 96 hoses.

FINDINGS · HWO-50K · SERIAL HWU-50-2218 · SOUR SERVICE
ComponentSpecAs-foundAfter rebuildStatus
Jack rod straightness (avg of 4)< 0.1 mm/m TIR0.42 mm/m0.06 mm/m↻ Straightened + re-chromed
Barrel bore (jacks)152.4 mm ± 0.05152.78 mm152.45 mm↻ Honed +0.05
Rod seal compoundNACE HNBRStandard NBRHNBR + FKM b/u↻ Replaced
Hi-pressure hose cover (boom)EN 856 4SP, soundUV-cracked, 60% pop.100% new, tagged↻ All 60 replaced
End fittings316 SS, NACEMix of plated CS + 316100% 316 SS↻ Replaced
Accumulator N₂ pre-charge1,000 psi · ≤ 6 mo700 psi · 19 mo1,000 psi · day 0↻ Re-charged, traceable
Relief valve set pressure5,250 psi ± 1005,180 psi5,250 psi↻ Re-certified
Cylinder wet-test, 525 bar30 min hold30 min, 0 bar drop✓ Pass · all 8
Hose proof-test, 2× WP5 min hold96 / 96 passed✓ Pass
/06

Outcome & sign-off.

The unit left our JAFZA yard on day 19, low-loaded back to the Rub’ al Khali on day 20, and was skidding on a wellhead by day 23. The operator made their Habshan slot with four days of margin to spare. All eight cylinders, the 96 new hoses and the four accumulators are covered under a single 12-month warranty for the assembled hydraulic system — not just parts, the whole circuit. We’ve since been added to the ADNOC AVL for hydraulic field services on the back of this job.

Result · summary

Eight rebuilt cylinders, 96 new hoses, four re-certed accumulators — and a workover unit fit for sour service for the next 12 months.

Delivered inside the operator’s 21-day window with four days of margin to spare. ADNOC vendor sign-off, NACE certs on every consumable, traceable from end fitting to nitrogen bottle. The unit went straight from low-loader to wellhead with zero rework on first power-up.

19days
Turnaround
96 / 96
Hoses proof-passed
8 / 8
Cyl. wet-test pass
12mo
System warranty
/07

The team on the job.

Five engineers logged time against this work order, all out of our Jebel Ali / JAFZA yard. If you call the workshop and ask about case 01, any of them can pull the file off the shelf within a minute.

  • Khalid Al MarzouqiField Lead, Jebel Ali. On-site inspection, accumulator re-charge, client-witness sign-off. First boots on the rig, last signature on the return packet.
  • Yusuf Al HashimiWorkshop Manager, Jebel Ali. Three-option quote, sign-off pack, customer-facing review. Owned the 42-page return packet and the ADNOC vendor verification.
  • Omar Al MaktoumLead Fitter, Jebel Ali. Cylinder disassembly, NACE seal-kit fitting, wet-test on the closed-loop rig at 525 bar. Eight cylinders, eight clean test reports.
  • Aisha Al SuwaidiMachinist, Jebel Ali. Rod straightening, 80 µm hard chroming, barrel honing to 0.05 mm oversize at 45° cross-hatch and Ra 0.4 µm.
  • Hassan Al AwadiHose-bay Supervisor, JAFZA. All 96 hose assemblies built and tagged in-house. End-fitting traceability on every swage, proof test record on every line.

Case file · INTAKE-2026-03-097 · WO-2026-1077 · Published 2026-04-12 · Updated 2026-05-09

SERVICE INTAKE · OPEN 24×7 · JEBEL ALI

If it leaks, hums, screams, drips, slips or simply refuses to move — we’d like a look at it.

Send us a photo, an SKU or a part on a pallet. We’ll do the rest.

An applications engineer will read your ticket inside one business day — no charge for the conversation, no obligation to use us.