Home/Services/Hoses/No. 08112 assemblies, 14 days, every hose tagged. A cold-stacked rig refitted for sour service.
Hoses · Sour Service · Industrial🇦🇪 UAE · Jebel Ali (JAFZA hose bay)CASE NO. 08 · APR 2026 · JAFZA HOSE BAY

112 assemblies, 14 days, every hose tagged. A cold-stacked rig refitted for sour service.

A drilling rig coming out of cold-stack needed a full hose-assembly refresh before re-mobilising to a sour-gas well in the GCC. The drilling engineer handed us a 112-line bill of materials with a 14-day deadline. Every assembly NACE MR0175, every fitting 316 stainless, every hose proof-tested and traceable back to the mill cert. Built in our JAFZA hose bay.

FIG. 01 · JAFZA hose bay during build week — 112 assemblies laid out by circuitPHOTO · H. AL AWADI · 2026-04-09
Asset
BOM-112· drilling rig refit
Assemblies
112· across 4 circuits
Build duration
14days
Proof-pass rate
112 / 112
H₂S service
NACE MR0175
/01

A cold-stacked rig and a 14-day window.

The rig had been cold-stacked for fourteen months on a yard outside Mussafah. The operator had won a sour-gas drilling contract in the GCC and the re-mobilisation date was non-negotiable. The drilling engineer walked into our Jebel Ali office on a Tuesday with a printed bill of materials — 112 hose assemblies, four circuits, every line called out by hose grade, ID, length, end-fitting type and orientation — and asked one question: can you build this in fourteen days, NACE compliant?

Cold-stack is hard on hydraulic hose. Fourteen months under Gulf sun, no flow, no maintenance: covers crack, swages corrode, elastomers go hard. A rig commissioning team can rebuild a top drive or recertify a BOP, but they cannot send a rig back to a sour-service well with field-built hose assemblies of unknown provenance. The operator wanted everything new, everything traceable, everything built to one specification. The risk was not the build — the risk was that a high-volume hose bay, building 112 assemblies in 14 days, would mix one EN-spec carbon-steel fitting into a NACE assembly by accident. One swage with the wrong elastomer in a sour-gas line is a fatality waiting for the right pressure spike.

What the operator told us

"112 assemblies, fourteen days, NACE — confirm or decline."

Drilling engineer brought a fixed BOM, four circuits, fourteen-day window. He needed a yes/no by end of day Tuesday so he could decide whether to source elsewhere. No room for negotiation on spec or schedule.

What the build risk actually was

High volume + NACE = procedural discipline, not throughput

A 112-assembly batch can be hit in 14 days by any reputable hose bay. The hard part is preventing one wrong fitting, one non-NACE elastomer, one untraceable coil from slipping into the batch. The build process had to make that mistake structurally impossible.

We confirmed by Tuesday evening on three conditions: the drilling engineer signed off on the BOM unchanged before we cut a single hose, every coil and every fitting got a mill-cert audit at the door before it touched the crimper, and every assembly carried a tag with circuit ID, swage number, proof-test date and batch trace from the day it left the bench. He signed. We started cutting Wednesday morning.

/02

112 assemblies across four circuits, all traceable.

The build broke into four parallel work-streams matched to the four circuits on the BOM. 60 hi-pressure boom-circuit hoses built to EN 856 4SP in 3/4" and 1" ID — four-spiral construction for the high-cycle jacking and pull-down lines, working pressure in the 6,000 psi range. 30 return-line and case-drain hoses built to EN 853 2SN in 1" and 1-1/4" ID for the lower-pressure circuits. 12 rotary-line hoses built to API 7K Grade D in 2" ID, 5,000 psi WP, fire-resistant cover — the only hoses on a drilling rig that have to survive a rig-floor fire long enough to shut the well in. 10 short-radius accumulator-circuit hoses built to EN 856 4SP in 1/2" ID for the BOP control manifold.

Every assembly across all four circuits used the same fitting and elastomer recipe: 316 stainless steel end fittings (the entire JAFZA stock of plated carbon-steel fittings was physically removed from the bay for the duration of the build, to make a wrong-fitting selection impossible), HNBR rod packing inside the swage, FKM (Viton) cover for sour-service compatibility. Proof-tested at 2× working pressure for 5 minutes on every assembly. Tagged with circuit ID, swage number, proof-test date and a batch-trace reference that links the assembly back to the mill cert (EN 10204 3.1) on the raw hose coil.

FIG. 02Day 8 — JAFZA crimp bay. Four-spiral EN 856 4SP coil being cut to length for a boom-circuit assembly. The yellow tag carries the BOM line number; nothing leaves the bay without it.
The difference between a hose shop and a NACE-compliant hose shop is one word — traceability. Anybody can crimp a swage. The question is whether you can hand the drilling engineer a binder that links every assembly back to the mill cert. If you cannot, you are not in sour service.— Hassan Al Awadi · Hose Bay Supervisor · JAFZA
/03

Four phases across fourteen days.

A high-volume NACE build is not a sprint — it is four sequential gates with hard go/no-go criteria at each one. Skip a gate and the cost shows up at proof-test, where you scrap assemblies. We hit zero scrap on this build because we did not skip the gates.

PHASE 01

BOM verify + raw-material inspection

Drilling engineer sign-off on the BOM. Mill-cert audit on every coil and every fitting at the door. Plated-carbon fittings removed from the bay.

Days 0 — 1
PHASE 02

Build

112 assemblies cut, swaged, marked. Crimp die-set verified before each new hose grade. BOM tag follows every assembly from cutting bench to crimp to QA.

Days 2 — 11
PHASE 03

Proof test + tag

Every assembly proof-tested at 2× WP for 5 min on closed-loop rig. Pass logged, tag printed: circuit ID, swage no., proof date, batch trace.

Days 12 — 13
PHASE 04

Delivery + sign-off

112 assemblies palletised by circuit. Traceability ledger handed over: mill certs, crimp logs, proof records, NACE certs. Drilling engineer signs.

Day 14
/04

The SOP we followed, line by line.

The full SOP-OG-014 covers every NACE-rated hose-assembly build that leaves the JAFZA bay. Below is the abridged version that was ticked off across the 14 days — 22 lines covering raw material inspection, crimp-setup verification, build, proof-test and batch traceability.

SOP-OG-014 · HOSE ASSEMBLY BUILD · REV 06 · NACE22 / 22 COMPLETE
Phase 01 · BOM verify + raw-material inspection
BOM signed by drilling engineer112 lines, four circuits, all spec callouts confirmed unchanged before cutting
H. AL AWADI
BOM PDF
Mill-cert audit on every hose coilEN 10204 3.1 cert checked against coil batch number on each of 14 coils received
A. AL SUWAIDI
Cert binder
Fitting cert audit · 316 SS only418 fittings inspected at the door; cert + heat number logged per fitting type
A. AL SUWAIDI
Heat log
Plated-CS fittings removed from bayAll non-316 fittings physically lifted out of the build bay before Day 2 cut start
O. AL MAKTOUM
Bay sweep
Elastomer batch verified · HNBR + FKMSour-service compound batch numbers logged on the build sheet for each circuit
A. AL SUWAIDI
Batch log
Phase 02 · Build · 112 assemblies
Crimp die-set verified · EN 856 4SPTest crimp on offcut measured against fitting OEM crimp chart before batch start
O. AL MAKTOUM
Crimp gauge
Build 60× hi-pressure hoses · EN 856 4SP3/4" and 1" ID, 316 SS fittings, BOM tag attached at cut and walked through to QA
O. AL MAKTOUM
Crimp bay
Build 30× return-line hoses · EN 853 2SN1" and 1-1/4" ID, 316 SS fittings, abrasion sleeve on case-drain run
O. AL MAKTOUM
Crimp bay
Build 12× rotary-line hoses · API 7K-D2" ID, 5,000 psi WP, fire-resistant cover, 316 SS hammer-union fittings
O. AL MAKTOUM
API bay
Build 10× accumulator-circuit hoses · EN 856 4SP1/2" ID short-radius assemblies for BOP control manifold; tight-bend swage check
O. AL MAKTOUM
Crimp bay
Crimp dimension log per assemblyCrimp diameter measured and logged against OEM spec for every one of 112 assemblies
A. AL SUWAIDI
Caliper + log
Phase 03 · Proof test + tag
Proof test rig calibration checkPressure transducer calibration cert verified in date; rig zeroed before batch start
A. AL SUWAIDI
Test rig
Proof test 60× EN 856 4SP at 12,000 psi2× WP held 5 min, leak rate logged; one assembly per rack proof-tested at a time
A. AL SUWAIDI
Closed-loop
Proof test 30× EN 853 2SN at 6,000 psi2× WP held 5 min on every return-line and case-drain assembly
A. AL SUWAIDI
Closed-loop
Proof test 12× API 7K-D at 10,000 psi2× WP held 5 min on every rotary-line assembly with hammer-union end loaded
A. AL SUWAIDI
API rig
Proof test 10× accumulator hoses at 12,000 psi2× WP held 5 min on short-radius BOP-circuit assemblies, tight-bend integrity logged
A. AL SUWAIDI
Closed-loop
Tag print + attach · 112 assembliesTag carries circuit ID, swage no., proof-test date, batch trace ref, NACE marker
A. AL SUWAIDI
Tag printer
Phase 04 · Delivery + sign-off
Palletise by circuitFour pallets — boom, return, rotary, accumulator — each circuit BOM stapled to the pallet
Y. AL HASHIMI
Workshop
Compile traceability ledger112 entries · mill cert ref + crimp log + proof record + NACE marker per assembly
A. AL SUWAIDI
PDF + paper
Drilling engineer sign-offOn-site witness at JAFZA bay; spot-check on 8 random assemblies against ledger entries
K. AL MARZOUQI
On-site
Issue NACE certificate per assembly112 individual NACE MR0175 certs issued, signed, scanned and emailed to drilling engineer
Y. AL HASHIMI
PDF
Low-loader release to rig yardFour pallets released on Day 14 evening; transport docs cross-referenced to ledger
K. AL MARZOUQI
Dispatch
/05

Spec table — what was built and how it tested.

The build sheet below shows the four circuits side by side: hose grade, ID range, end-fitting material, elastomer compound, proof-test pressure and pass rate. Four rows are highlighted as the critical findings — the ones the drilling engineer audited on the spot before signing.

BUILD · BOM-112 · DRILLING RIG REFIT · SOUR SERVICE NACE MR0175
ComponentSpecAs-foundAfter rebuildStatus
Hi-pressure boom-circuit hoseEN 856 4SP · 6,000 psi WP60 assemblies cut60 / 60 proof-passed at 12,000 psi✓ Pass · all 60
Return + case-drain hoseEN 853 2SN · 3,000 psi WP30 assemblies cut30 / 30 proof-passed at 6,000 psi✓ Pass · all 30
Rotary-line hoseAPI 7K Grade D · 5,000 psi WP12 assemblies cut12 / 12 proof-passed at 10,000 psi✓ Pass · all 12
Accumulator-circuit hoseEN 856 4SP · 1/2" ID short-radius10 assemblies cut10 / 10 proof-passed at 12,000 psi✓ Pass · all 10
End-fitting material316 SS · NACE MR0175418 fittings cert-audited100% 316 SS · 0 plated-CS in bay✓ Confirmed
Rod packing inside swageHNBR · sour-service rated4 batch numbers verified100% HNBR · batch logged per assembly✓ Confirmed
Hose cover compoundFKM (Viton) · sour-service ratedCoil cover spec verified112 / 112 FKM cover✓ Confirmed
Proof-test pressure2× WP held 5 minTest rig cal cert in dateHeld to spec on 112 / 112✓ Pass
Mill-cert traceabilityEN 10204 3.1 per coil14 coils received with cert100% logged · ledger ref per assembly✓ Logged
Crimp-dimension verificationOEM crimp chart ± 0.1 mmDie-set verified per grade112 / 112 in spec · logged per assembly✓ Pass
NACE certificate per assemblyMR0175 / ISO 15156112 / 112 issued✓ Issued
/06

112 / 112 first-pass, ledger handed over on Day 14.

Every assembly passed proof-test on first attempt. No scrap, no re-builds, no slipped tags. The traceability ledger went over to the drilling engineer on Day 14 evening — 112 entries, each with the mill cert reference for the raw coil, the crimp log entry for the fitting, the proof-test record and an individual NACE MR0175 certificate. He spot-checked eight assemblies at random against the ledger before signing. The four pallets — boom, return, rotary, accumulator — were on a low-loader to the rig yard at Mussafah by midnight. The rig re-mobilised to its sour-gas well three weeks later, on schedule.

Result · summary

112 assemblies built in 14 days, every one NACE-traceable from end-fitting to mill cert.

Delivered inside the drilling engineer's window with zero scrap on the proof bench. The traceability ledger is the deliverable that mattered — without it, the assemblies cannot legally go on a sour-service well, no matter how well they are crimped. JAFZA bay closed the build with 112 individual NACE certs, four pallets, and one signed BOM.

14days
Build duration
112 / 112
Proof-test first pass
112 / 112
Mill-cert traceable
0
Scrap or rebuilds
/07

The team on the bench in JAFZA.

Five engineers logged time against this build, all out of the JAFZA hose bay and the Jebel Ali workshop. The build is a team sport when the volume is high and the standard is NACE — every gate has a different signature on it. If you call the bay and ask about case 08, any of them can pull the file.

  • Hassan Al AwadiHose Bay Supervisor, JAFZA. BOM sign-off coordination, build-bay sequencing, daily progress against the 14-day schedule
  • Aisha Al SuwaidiQA · Materials & Traceability, JAFZA. Mill-cert audit on every coil, fitting heat-number log, crimp-dimension log, traceability ledger
  • Omar Al MaktoumLead Crimp Operator, JAFZA. Die-set verification per hose grade, all 112 swage operations across the four circuits
  • Yusuf Al HashimiWorkshop Manager, Jebel Ali. Build-bay sweep of plated-CS fittings, palletisation by circuit, NACE certificate issuance
  • Khalid Al MarzouqiField Lead · Sign-off, Jebel Ali. On-site witness for drilling engineer sign-off, dispatch coordination to the rig yard at Mussafah

Case file · INTAKE-2026-04-114 · WO-2026-1184 · Published 2026-05-02 · Updated 2026-05-09

SERVICE INTAKE · OPEN 24×7 · JEBEL ALI

If it leaks, hums, screams, drips, slips or simply refuses to move — we’d like a look at it.