Choke & Kill · API 16C · Oilfield🇦🇪 UAE · Jebel AliCASE NO. 06 · FEB 2026 · BAY 1 / WORKSHOP

A 3-1/16" 10K choke & kill manifold, eight gate valves, and the trim swap that bought it five more years of sour service.

A 10,000 psi choke & kill stack from ADNOC Offshore Lower Zakum landed in our Jebel Ali bay with the API 16C clock at 4 years 11 months. Twenty-eight days later it left with eight rebuilt gate valves, two re-trimmed chokes, every metallic part NDT-cleared, a 15,000 psi shell-test record on every body, and a fresh five-year recert stamp valid through 2031.

FIG. 01 · 3-1/16" 10K choke & kill manifold on the bench · Bay 1, Jebel Ali · day 2PHOTO · Y. AL HASHIMI · 2026-02-04
Asset
C&K-3116-10K· API 16C
Gate valves
8· 3-1/16" 10K
Chokes
2· 1× hyd / 1× man
Turnaround
28days
Sour service
NACE MR0175
/01

A 5-year clock, a sour-service stack, and a stamp that was about to expire.

The transporter rolled in on a Tuesday afternoon. A 3-1/16" 10,000 psi choke & kill manifold from ADNOC Offshore — Lower Zakum platform, sour-service trim, painted ADNOC red — sat strapped to the trailer with a stamped tag that said the API 16C 5-year recert was due in 27 days. It came in alongside a BOP stack from the same platform that we recerted in parallel; this is the choke and kill side of that intake.

The customer brief was tight and honest: full API 16C 5-year recertification per the standard, NACE MR0175 / ISO 15156 compliance, hydrostatic shell test at 1.5× working pressure, function test on every valve and choke, and a clean FAT pack the operator could hand to ADNOC HSE without a single yellow tag. The deadline was Lower Zakum's next workover slot. Twenty-eight days. Eight gate valves and two chokes. Every body, every stem, every stud — on the bench.

What the operator told us

"Strip, NDT, trim swap, hydrotest. Standard 5-year recert."

ADNOC sent the manifold in with a clean inbound report: in-service for 4 years 11 months, no recorded kicks above 6,500 psi, no visible external corrosion. The asks: full strip, NACE-compliant trim, NDT scope per API 16C Annex F, 15,000 psi shell test, fresh recert.

What the inspection actually found

Three seats eroded from kick cycling, two stems with chloride pitting, half the bolting non-NACE

Strip-down day 3: 3 of 8 gate-valve seats showed cyclic-pressure erosion at the seal land. 2 stems carried chloride pitting consistent with sour-service exposure. The hydraulic choke's orifice was 0.6 mm out vs OEM. And a count of the bolting found 38 of 64 studs were non-NACE B7 — they had to come out.

API 16C is unambiguous on this. A 5-year recert is not a clean-and-paint exercise; it is a full strip, NDT pass, hydrotest hold and FAT certification — and on a sour-service stack, the trim must be NACE MR0175 / ISO 15156 compliant from seat to packing to bolting. The operator's ask was correct. The inspection just told us how much trim was actually coming out of the boxes.

/02

Strip everything. NDT everything. Trim everything. Stamp it for five more years.

Twenty-eight days, end to end. We stripped all 8 gate valves and both chokes down to bare bodies, sent every metallic part through MPI + UT + hardness verification per NACE MR0175 (≤ 22 HRC ceiling), replaced every seat in the stack with Inconel-625-clad NACE-trim seats, swapped every stem packing to HNBR + FKM back-up, replaced both choke trim sets with OEM dimensional kits, and pulled all 64 body studs to put ASTM A193 B7M / 2HM sour-service bolting back in. Every body went through a hydrostatic shell test at 1.5× WP — 15,000 psi held for 30 minutes — and every valve got a function-cycle test on the closed-loop rig before it went into the FAT pack.

The bodies themselves — AISI 4130 alloy steel forgings, 10K class — passed UT and MPI with no rejectable indications. That was the easy part. The harder part was the stem-packing chamber on two of the gate valves: chloride pitting deep enough that we re-machined the chamber 0.15 mm under and fitted oversize HNBR seals to rebuild the seal land cleanly. That work is in the spec table at /05.

FIG. 02Day 14 — Bay 1 trim bench. All 8 gate-valve seats laid out in NACE MR0175 trim alongside the as-found seats they replaced. Inconel-625 cladding on every sealing surface; B7M studs fanned out below.
On a sour-service recert what matters most is what is NOT in the trim. No standard B7 studs. No NBR seals. No plain carbon-steel seat inserts. You don't pass API 16C by hitting numbers — you pass it by having nothing in the assembly that violates NACE.— Omar Al Maktoum · Lead Valve Technician · Jebel Ali
/03

Four phases on the bench, twenty-eight days, no overtime.

Every API 16C 5-year recert we run goes through the same four phases. The clock varies with what the bodies and trim hand us; the phase names don't change. This one ran clean to the day.

PHASE 01

Receipt, strip & survey

Manifold offloaded into Bay 1, photo log, traceability tags on every body. Full strip-down to bare metal — bonnets off, gates out, choke trim out, all 64 studs pulled.

Days 0 — 3
PHASE 02

NDT & material verification

MPI on every machined surface, UT on every body, hardness test on every metallic component. NACE MR0175 ≤ 22 HRC ceiling enforced. Mill certs cross-checked against EN 10204 3.1 / 3.2.

Days 4 — 10
PHASE 03

Trim swap & rebuild

New Inconel-625-clad seats fitted, HNBR + FKM packing repacked, both choke trim sets swapped, all 64 studs replaced with B7M, torqued to API 6A spec.

Days 11 — 22
PHASE 04

Hydrotest, function & FAT

15,000 psi shell hold, 30 min, on every body. Function cycle on every gate valve, choke open/close on both chokes. FAT pack signed by ADNOC vendor rep on day 28.

Days 23 — 28
/04

The SOP we followed, line by line.

Below is the abridged checklist from SOP-OG-018, the procedure we use for every API 16C 5-year recert in the Jebel Ali bay. The full document runs 41 lines; this is the subset that was ticked off on this manifold, in order.

SOP-OG-018 · CHOKE & KILL API 16C 5-YEAR RECERT · REV 06 · NACE23 / 23 COMPLETE
Phase 01 · Receipt, strip & survey
Inbound traceability tags on every bodyBay 1 receipt — manifold serial, 8× valve bodies, 2× choke bodies, 64× studs all logged
Y. AL HASHIMI
Tag printer
Full strip to bare metalBonnets off, gates out, choke trim out, every stud pulled, every elastomer disposed
O. AL MAKTOUM
Workshop
As-found dimensional & visual surveySeat sealing land, stem chamber, choke orifice, body bore — measured against OEM print
A. AL SUWAIDI
Micrometer
Bolting audit64 studs counted, marked for grade — found 38× B7 (non-NACE), all flagged for replacement
A. AL SUWAIDI
Hardness pen
Phase 02 · NDT & material verification
MPI on every machined surfaceWet-fluorescent MPI per ASTM E709 — every body, bonnet, gate, stem, choke needle
A. AL SUWAIDI
MPI bench
UT on all body forgingsStraight-beam UT per API 16C Annex F — 8× valve bodies + 2× choke bodies + manifold spool
A. AL SUWAIDI
UT probe
Hardness verification — NACE MR0175≤ 22 HRC ceiling enforced on every wetted metallic part. 3 readings per part, averaged
A. AL SUWAIDI
Brinell
Mill cert cross-checkEN 10204 3.1 / 3.2 certs pulled and cross-referenced against heat numbers stamped on parts
F. AL MANSOORI
Cert file
Phase 03 · Trim swap & rebuild
Re-machine 2× stem packing chambersChloride pits 0.08 mm deep cleaned out at 0.15 mm undercut; oversize HNBR fitted
H. AL AWADI
CNC lathe
Fit 8× Inconel-625-clad NACE seatsOEM seat kits, factory-clad sealing surfaces, fitted to torque per OEM 6A spec
O. AL MAKTOUM
Press fit
Repack 8× stems · HNBR + FKMHNBR primary + FKM back-up, all NACE MR0175 grade, lubricated with NACE-rated grease
O. AL MAKTOUM
Pack tool
Swap both choke trim setsHyd choke: new tungsten-carbide needle + cage. Manual choke: new TC seat + needle
O. AL MAKTOUM
Workshop
Replace 64× body studs · B7M / 2HMASTM A193 B7M studs + ASTM A194 2HM nuts, torqued to API 6A spec, witness-marked
H. AL AWADI
Torque wrench
Reassemble manifold spoolValves and chokes assembled to spool body in OEM configuration, ring gaskets renewed
O. AL MAKTOUM
Workshop
Phase 04 · Hydrotest, function & FAT
Hydrostatic shell test · 15,000 psi · 30 min1.5× 10K WP, held 30 min per body, leak-rate ≤ 0 psi drop on all 8 valves + 2 chokes
A. AL SUWAIDI
Hydrotest rig
Function test · every gate valveOpen/close cycle, hand-wheel torque measured, gate-stem indicator verified — all 8 pass
O. AL MAKTOUM
Test bench
Function test · both chokesHyd choke: full open/close vs HMI position. Manual choke: full sweep, indicator verified
O. AL MAKTOUM
Test bench
NACE MR0175 / ISO 15156 compliance certCert issued covering every wetted metallic part + every elastomer in the assembly
F. AL MANSOORI
QA pack
API 16C 5-year recert stampRecert tag stamped on manifold spool: valid through 2031-02, signed by Engineering Authority
F. AL MANSOORI
Stamp
Client-witnessed FATADNOC vendor rep on bench day 28 — every test re-verified, FAT pack signed live
K. AL MARZOUQI
On-bench
Issue FAT pack58 pp · NDT records, hardness logs, hydrotest curves, mill certs, NACE certs, photos × 42
F. AL MANSOORI
PDF + paper
/05

What we measured, before and after.

Below is what the as-found survey returned against OEM and API 16C tolerance, and what the rebuild handed back. Four findings would have failed an API 16C audit on the spot — all four are highlighted, all four were corrected in Phase 03.

FINDINGS · C&K-3116-10K · SERIAL CKM-3116-2087 · SOUR SERVICE
ComponentSpecAs-foundAfter rebuildStatus
Gate-valve seat sealing land (avg of 8)OEM contour, no erosion3 of 8 eroded, 0.4 mm8 of 8 new, OEM↻ All 8 seats replaced
Gate-valve seat materialNACE MR0175 trimB7 / std carbideInconel-625 clad↻ Replaced — NACE
Stem packing materialNACE HNBR + FKMStandard NBRHNBR + FKM b/u↻ Replaced
Stem chamber surface (2 of 8)Ra ≤ 0.8 µm, no pitsCl⁻ pits, 0.08 mm0.15 mm undercut, OS pack↻ Re-machined
Body stud grade (count of 64)ASTM A193 B7M (NACE)38× B7 / 26× B7M64× B7M↻ All 64 replaced
Hyd choke needle/orificeOEM dim ± 0.1 mm+0.6 mm erosionNew TC kit, OEM↻ Trim swapped
Manual choke trimOEM TC seat + needleLight wear, in tolNew TC kit, OEM↻ Trim swapped
Body NDT (MPI + UT)No rejectable indications0 indications0 indications✓ Pass · 8/8 + 2/2
Hardness (every wetted part)NACE ≤ 22 HRC18 — 21 HRC range17 — 21 HRC range✓ NACE compliant
Hydrostatic shell test, 1.5× WP15,000 psi · 30 min hold30 min, 0 psi drop✓ Pass · 8/8 + 2/2
Function test · gate valvesFull open/close cycle8 of 8 cycled✓ Pass
Function test · chokesOpen/close, position OK2 of 2 cycled✓ Pass
/06

Five years on the stamp, NACE compliance certified, back to Lower Zakum.

On day 28, the ADNOC vendor rep walked the FAT pack on the bench and signed every page live. The manifold left Jebel Ali on day 29, low-loaded back to the Lower Zakum deployment yard, and was scheduled for redeployment on the next workover slot. The recert stamp on the spool reads valid through February 2031. NACE MR0175 / ISO 15156 compliance is certified on every wetted metallic part and every elastomer in the assembly. The 58-page FAT pack is on file at the operator's document control.

Result · summary

Eight rebuilt gate valves, two re-trimmed chokes, every body NDT-cleared and 15K-tested, and a 5-year API 16C recert stamp valid through 2031.

Delivered on schedule at 28 days, no overtime, no rework. ADNOC vendor witness signed the FAT pack on the bench on day 28. NACE MR0175 / ISO 15156 compliance certified end-to-end — every seat, every packing, every stud — backed by EN 10204 3.1 / 3.2 mill certs.

28days
Turnaround
10 / 10
15K shell test pass
8 / 8 + 2 / 2
Function test pass
60mo
API 16C recert validity
/07

The team on the bench.

Six engineers logged time against this work order in the Jebel Ali bay. If you call the workshop and ask about case 06, any of them can pull the file in under a minute.

  • Yusuf Al HashimiWorkshop Manager, Jebel Ali. Inbound receipt, bay scheduling, FAT pack release, ADNOC vendor liaison
  • Omar Al MaktoumLead Valve Technician, Jebel Ali. Strip-down on all 8 gate valves, trim fit on every seat, stem repack, choke trim swap, function test
  • Aisha Al SuwaidiQA / NDT Inspector, Jebel Ali. MPI + UT + hardness on every metallic part, hydrostatic test witness, NACE compliance audit
  • Hassan Al AwadiMachinist, Jebel Ali. Re-machined 2× stem chambers to 0.15 mm undercut, B7M stud torque, ring-gasket fitment
  • Fatima Al MansooriEngineering Authority, Jebel Ali. API 16C recert sign-off, mill cert reconciliation, NACE MR0175 / ISO 15156 cert issue, recert stamp
  • Khalid Al MarzouqiField Lead, Jebel Ali. On-bench client liaison, FAT walk-through with ADNOC vendor rep, redeployment coordination

Case file · INTAKE-2026-02-038 · WO-2026-1018 · Published 2026-03-04 · Updated 2026-05-09

SERVICE INTAKE · OPEN 24×7 · JEBEL ALI

If it leaks, hums, screams, drips, slips or simply refuses to move — we’d like a look at it.

Send us a photo, an SKU or a part on a pallet. We’ll do the rest.

An applications engineer will read your ticket inside one business day — no charge for the conversation, no obligation to use us.