Home/Services/BOP & pressure control/No. 03A 5-year recert on a 13-5/8" 10K Cameron Type-U — and an annular that came off the bench faster than it went on.
BOP & Pressure Control · Recert · Oilfield🇦🇪 UAE · Jebel AliCASE NO. 03 · FEB 2026 · BAY 1 / WORKSHOP

A 5-year recert on a 13-5/8" 10K Cameron Type-U — and an annular that came off the bench faster than it went on.

ADNOC Drilling pulled a 13-5/8" 10,000 psi Cameron Type-U double-ram BOP for its mandatory API 16A major inspection. The brief was "the cheapest legal recert that gets the asset back on the rig." What we delivered was a stripped-to-component rebuild, NDT on every metallic, a NACE-traceable elastomer pack, and a shell that held 15,000 psi for 30 minutes with zero drop.

FIG. 01 · 13-5/8" 10K Cameron Type-U double-ram BOP, day 14 — bonnets open, ram blocks out for NDTPHOTO · O. AL MAKTOUM · 2026-02-15
Asset
13-5/8"· Cameron Type-U
WP
10,000· psi
Hydrotest
15,000· psi · 30 min
Turnaround
42days
H₂S service
NACE MR0175
/01

A 5-year clock that had run out.

A 13-5/8" 10,000 psi Cameron Type-U double-ram BOP arrived on a low-loader at our Jebel Ali yard on a Tuesday morning, with a 5-year API 16A major-inspection clock that had run out 11 days earlier. The operator was an ADNOC Drilling rig in Abu Dhabi and the message on the pre-intake form was three words long. "Recert. Cheapest. Rig."

API STD 53 doesn't care about your spread rate. Once the 5-year window on the BOP closes, the asset cannot be put back on a wellhead without a full strip-down, dimensional and NDT scope, soft-goods replacement, hydrostatic shell test and function test — witnessed, certified, packaged. Skip a step and the well-control insurance walks. The operator knew that. The operator also knew the rig was off-hire by the day. The economic pressure said "minimum legal." The standard said "everything in the procedure, in the order written." We work for the standard.

What the operator told us

"Cheapest legal recert. Get it back on the rig."

BOP pulled at the 5-year mark per API 16A schedule. Operator wanted the minimum-spec recert — replace soft goods, hydrotest, function test, certify. No "while you're in there." Asset off-hire and a rig waiting on the wellhead.

What the inspection actually found

Bonnet seals end-of-life, hub-face scoring, shear edge at the limit

HNBR bonnet-seal degradation visible the moment the bonnets came open. One pipe-ram block with light hub-face scoring on the metal seal land. One blind-shear ram with cutting-edge wear inside 0.3 mm of the OEM scrap dimension. None of those go back on a rig without intervention.

The "minimum legal" recert and the recert that this BOP actually needed were not the same recert. We rang ADNOC Drilling at 14:20 on the third day with photos, dimensional sheets, and a single-page PDF that listed every finding alongside the standard reference that flagged it. The PO came back inside 36 hours. Nobody argues with API 16A in writing.

/02

Strip to component, NDT every metallic, replace every soft good.

We took the BOP down to component level — bonnets off, ram blocks out, operating cylinders separated, locking screws backed out, every fastener tagged by position. Every metallic part went through the full API 16A Annex C NDT scope: magnetic-particle inspection (MPI) on the ferrous bodies, ultrasonic thickness on the body wall and bonnet flanges, dimensional verification against the original Cameron datum, dye-penetrant on every critical sealing surface, and Rockwell-C hardness on each forged component to confirm ≤ 22 HRC per NACE MR0175 / ISO 15156. The body and ram blocks are AISI 4130 alloy steel forging with Inconel-625 cladding on the metal-to-metal sealing lands; bonnet bolting is ASTM A193 B7M studs with 2HM nuts, all sour-service rated. Every certificate is EN 10204 3.1 minimum, 3.2 on the body and ram blocks.

Every elastomer in the BOP got replaced — no exceptions, no "looks fine." Bonnet seals, ram packers, top seals, annular packing element, piston seals, wear rings — all renewed in HNBR sour-service grade from the Cameron OEM kit, with FKM back-ups where the design calls for them. The scored hub face on the No. 2 pipe-ram block was reconditioned to the OEM datum and the seal land re-machined. The blind-shear ram with edge wear was retired and replaced from OEM stock. Reassembly was torqued in sequence with calibrated wrenches and recorded line-by-line.

FIG. 02Day 22, Bay 1. Bonnet open, lower ram cavity exposed, shear ram block on the bench. Hub face is the polished annulus on the bonnet flange — that's the metal seal land that controls 10,000 psi.
Hardness control is the safety story on a sour-service BOP. Twenty-two HRC isn't a target — it's a ceiling. Every forging, every stud, every nut, individually verified. If the file isn't there, the part doesn't go back in.— Aisha Al Suwaidi · QA / NDT Inspector · Jebel Ali
/03

Four phases, 42 days, one signed FAT pack.

A 5-year API 16A recert on a 13-5/8" 10K stack is not a job you finish faster by working harder. It's a procedure. We run every Cameron Type-U recert through the same four phases.

PHASE 01

Receipt & condition assessment

BOP off the truck, weighed, photographed, lifted to the bench. Visual, fluid drain, witness sample. Pre-strip dimensional and a 12-page intake report on the operator's desk by day 3.

Days 0 — 3
PHASE 02

NDT & dimensional

Strip to component. MPI on every ferrous part, UT thickness on body and bonnet flanges, dimensional vs OEM datum, hardness Rockwell C, dye-penetrant on sealing surfaces. Findings logged.

Days 4 — 12
PHASE 03

Recondition & rebuild

Hub face re-machined. Worn shear ram replaced. Every elastomer renewed in HNBR. Reassemble in OEM sequence with torque records on every fastener. Operating cylinders honed and resealed.

Days 13 — 30
PHASE 04

Test, FAT & release

Hydrostatic shell at 1.5× WP = 15,000 psi, 30 min hold. Function test per API STD 53. Closure-time records on each cavity. ADNOC-witnessed sign-off, 96-page FAT pack, low-loader to the rig.

Days 31 — 42
/04

The SOP we ticked off, line by line.

Below is the abridged SOP that governs a Cameron Type-U 5-year major recert in our shop. The full document runs 78 lines and four annexes. This is the subset that was checked off, dated and signed on this work order.

SOP-OG-016 · BOP 5-YEAR API 16A RECERT · REV 07 · NACE47 / 47 COMPLETE
Phase 01 · Receipt & condition assessment
Goods-in inspection & weighbridgeBOP weighed at 14,820 kg dry; photo log against waybill; visible damage survey
Y. AL HASHIMI
Crane bay
Hydraulic fluid drain & witness sample38 L drained from operating circuit; sample retained for cleanliness ISO 4406
O. AL MAKTOUM
Drain rig
Pre-strip dimensionalBore, bonnet flange flatness, bonnet bolt-hole alignment vs Cameron datum
A. AL SUWAIDI
CMM + bore mic
Sour-service classification confirmH₂S partial pressure on rig data > 0.3 kPa — NACE MR0175 / ISO 15156 applies in full
QA
Operator gas data
Intake report · 12 pp PDFPhotos, baseline dimensions, fluid sample result, recommended NDT scope
F. AL MANSOORI
PDF
Phase 02 · NDT & dimensional
Bonnet break-out & ram extractionHydraulic torque tool, breakout sequence per Cameron service manual; rams to bench
O. AL MAKTOUM
HYTORC
MPI · all ferrous componentsWet fluorescent, body, ram blocks, bonnets, locking-screw bores; per ASME V Art. 7
A. AL SUWAIDI
MPI bench
UT thickness · body & bonnet flangesMin wall vs OEM scrap dim; 24 readings per body, 8 per bonnet flange
A. AL SUWAIDI
UT gauge
Hardness Rockwell C · NACE MR0175All forgings tested ≤ 22 HRC; every test logged with location & operator
A. AL SUWAIDI
Hardness tester
Dimensional vs OEM datumBore, ram block face, hub face, bonnet flange — all to ± 0.05 mm tolerance
A. AL SUWAIDI
CMM
Dye-penetrant on sealing surfacesHub faces, ram block seal lands, bonnet seal grooves; per ASME V Art. 6
A. AL SUWAIDI
DPI kit
NDT findings report · 18 pp PDFOne row per part, status, action; basis for change-order PO
F. AL MANSOORI
PDF
Phase 03 · Recondition & rebuild
Hub face re-machining · No. 2 pipe-ram bonnetLight scoring removed; flatness restored to ≤ 0.025 mm vs datum; surface Ra ≤ 0.4 µm
H. AL AWADI
CNC mill
Replace blind-shear ram cutting edgeOEM Cameron part, EN 10204 3.2 cert, hardness verified ≤ 22 HRC on receipt
O. AL MAKTOUM
OEM stock
Renew all elastomers · HNBR sour-serviceBonnet seals, ram packers, top seals, annular element, piston seals, wear rings — full kit
O. AL MAKTOUM
Cameron kit
Operating cylinders strip & resealPistons polished, bores honed, HNBR seals; bench-tested at 3,000 psi pre-install
H. AL AWADI
Hone bar
Reassemble per OEM sequenceBonnets fitted, locking screws set, ram blocks indexed; every torque recorded
O. AL MAKTOUM
Calibrated TQ
Bonnet bolting · A193 B7M / 2HMNew studs and nuts to OEM torque chart; per API 6A bolting practice
O. AL MAKTOUM
HYTORC
Phase 04 · Test, FAT & release
Hydrostatic shell test · 1.5× WP15,000 psi held 30 min · zero pressure drop measured at 0.1% gauge resolution
A. AL SUWAIDI
Hydrotest rig
Function test per API STD 53Open/close timing on every cavity; closure ≤ 30 s requirement (largest cavity)
O. AL MAKTOUM
Function rig
Closure-time records · all cavitiesAnnular 4.8 s, upper pipe 3.2 s, blind-shear 4.1 s, lower pipe 3.4 s — all well inside spec
A. AL SUWAIDI
Stopwatch + logger
ADNOC-witnessed sign-offADNOC Drilling engineer present for shell + function tests; counter-signature on cert
F. AL MANSOORI
On-site
FAT package · 96 ppNDT records, hardness logs, torque sheets, hydrotest curve, function records, recerts cert
F. AL MANSOORI
PDF + paper
API 16A 5-year cert issuedNew recert sticker dated 2026-02-26; valid until 2031-02-26 per API 16A schedule
F. AL MANSOORI
Cert
Low-loader release to rigBOP loaded with shell-pressurised valves, dust covers, transit log; rig-ready
Y. AL HASHIMI
Logistics
/05

The numbers, before and after.

Below is what we measured on the BOP against API 16A and OEM Cameron tolerance. Four findings would have failed an audit if the unit had been put back on the rig as-is — every one was closed out in Phase 03.

FINDINGS · 13-5/8" 10K CAMERON TYPE-U · SERIAL CAM-U-1358-7041 · SOUR SERVICE
ComponentSpecAs-foundAfter rebuildStatus
Bonnet seal compoundHNBR sour-serviceOriginal HNBR, end-of-lifeNew HNBR · OEM kit↻ Renewed all 4
Hub face flatness · No. 2 bonnet≤ 0.025 mm vs datum0.18 mm + scoring0.012 mm · Ra 0.32 µm↻ Re-machined
Blind-shear ram cutting edge≥ OEM scrap dim0.28 mm above scrapNew OEM block↻ Replaced
Body hardness · all locations≤ 22 HRC · NACE MR017519.4 — 21.6 HRCNo change · in spec✓ Pass
Bonnet stud hardness · A193 B7M≤ 22 HRC20.8 HRC avg (n=24)New B7M · 21.1 avg↻ All studs replaced
Body wall UT thickness · min≥ 95% of OEM nominal98.2% of nominalNo change · pass✓ Pass
Annular packer geometryOEM Cameron Type-U12% taper deformationNew element · OEM↻ Replaced
Inconel-625 cladding · seal landsNo cracks / DPI cleanDPI cleanDPI clean post-test✓ Pass
Hydrostatic shell test15,000 psi · 30 min hold15,000 psi · 0 psi drop✓ Pass
Annular closure time≤ 30 s · API STD 535.4 s (last rig record)4.8 s✓ Pass · −0.6 s
Pipe-ram closure time · upper≤ 30 s · API STD 533.4 s3.2 s✓ Pass
Blind-shear closure time≤ 30 s · API STD 534.6 s4.1 s✓ Pass
/06

Recert stamp, FAT pack, back on the rig.

The BOP came off the test bench at 11:40 GST on day 41 with the ADNOC Drilling rig engineer counter-signing the hydrotest chart. The FAT package — 96 pages, two paper copies, one PDF, one ZIP of NDT records and hardness logs — was issued on the morning of day 42. The unit went on a low-loader at 14:00 the same afternoon and was on the rig floor in Abu Dhabi by the next morning. The new API 16A 5-year recert is valid until February 2031. The annular closure time came off the bench 0.6 seconds faster than it went on — a small finding, but in BOP work the small numbers are the ones that matter.

Result · summary

Cameron Type-U 13-5/8" 10K BOP back on the rig with a fresh 5-year API 16A recert and an annular that closes faster than the day it left.

Full strip-to-component rebuild, NDT on every metallic, NACE-traceable elastomer pack, hydrotest at 15,000 psi held 30 minutes with zero drop, ADNOC-witnessed function test, 96-page FAT pack issued. Recert valid 2026 to 2031.

42days
Bench TAT
15,000psi · 0 drop
Hydrotest
4.8 / 30s
Annular closure (limit)
5yr
Recert validity
/07

The team on the bench.

Six engineers logged time against this work order — all in Jebel Ali, all on the same shop floor. If you call the workshop and ask about case 03, any of them can pull the file off the shelf.

  • Yusuf Al HashimiWorkshop Manager, Jebel Ali. Goods-in, planning, weighbridge, low-loader release. Owns the work-order file end to end.
  • Khalid Al MarzouqiField Lead, Jebel Ali. Operator liaison, change-order PO, FAT scheduling with the ADNOC Drilling rig engineer.
  • Aisha Al SuwaidiQA / NDT Inspector, Jebel Ali. MPI, UT thickness, hardness Rockwell C, dimensional CMM, dye-penetrant. Signed every NDT record.
  • Omar Al MaktoumLead BOP Technician, Jebel Ali. Strip-down, ram extraction, elastomer fit, reassembly to OEM torque chart, function test.
  • Hassan Al AwadiMachinist, Jebel Ali. Hub-face re-machining on the No. 2 pipe-ram bonnet, operating cylinder hone and reseal.
  • Fatima Al MansooriEngineering Authority, Jebel Ali. Intake report, NDT findings report, FAT pack compilation, API 16A recert sign-off.

Case file · INTAKE-2026-02-014 · WO-2026-1041 · Published 2026-03-08 · Updated 2026-05-09

SERVICE INTAKE · OPEN 24×7 · JEBEL ALI

If it leaks, hums, screams, drips, slips or simply refuses to move — we’d like a look at it.

Send us a photo, an SKU or a part on a pallet. We’ll do the rest.

An applications engineer will read your ticket inside one business day — no charge for the conversation, no obligation to use us.